The Hinchingbrooke Next Steps project timeline
Key diary milestones
| Phase 4 – ITPD2 (invitation to participate in dialogue 2) | |
| ITPD2 issued | 12/04/10 |
| ITPD2 submission deadline | 26/07/10 |
| ITPD2 evaluation | 27/07/10 – w/c 27/09/10 |
| Confirmation of bidders recommended to proceed to ITT | w/c 27/09/10 |
| Phase 5 – ITT (invitation to tender) | |
| ITT issued | 04/10/10 |
| ITT submission deadline | 18/10/10 |
| ITT evaluation | 18/10/10 – 04/11/10 |
| Preferred franchisee appointed | w/c 15/11/10 |
| Phase 6 – Approvals (subject to confirmation of approval & public involvement process) | |
| Full business case / approvals | 30/11/10 – 31/01/11 |
| Contract award & signature | 01/02/11 |
| Service commencement | 01/06/11 |
| Staff and public involvement | Ongoing |
Table updated 28 June 10.